Project
Media City Tower 3
Location
Salford
Client
Vermont Construction
Description
Dual-utility solution
- 1.5MVA substation
- 6.6kV cables to be laid from the point of connection
- Seven 300mm2 LV cables, 15m of HV earth cable and 170mm copper earth cable installed between the substation and ground floor plantroom
- Coordination with water supply provider
- 1MVA connection with a HV metered temporary builders’ supply
Group Head Office
Eleanor House. Newport Pagnell Road West,
Wootton, Northampton NN4 7JJ
03303 209 899
what3words: ///groups.lifts.cared
Northern office
6500 Daresbury Park, Daresbury,
Warrington WA4 4GE
what3words: ///scratches.glossed.trifling
Southern Office
Venture House, 2 Arlington Square, Downshire Way,
Bracknell, RG12 1WA
what3words: ///view.tune.rods