Our brief
Electricity: A new 33/11kV primary substation to supply 8MVA. A 100m offsite excavation route for 33KkV cabling and a bespoke substation design to enable shared ownership of an 11klV board.
Gas: A metered gas service
How we delivered
- Dedicated project manager appointed
- Matrix team seconded to site
- Bespoke substation designed and delivered
- Development energised within nine months