Project
Frontier Park
Location
Blackburn
Client
Barnfield Construction / Utility Connections
Description
- 5MVA load – increasing to 10MVA
- 1.5km off site medium pressure gas installation
- 3km off site electric HV cable connection to a Primary Substation
- Worked with Electricity North West to complete a 33kV diversionary works around the perimeter of the site
- Individual substations, individual gas meters and water supplies to all units
- Our Group IDNO, UKPD adopted the 11kV point of connection.