9th October update
Rowley Road
The cable ducting has now been installed in this area. Further updates will be provided on when we’ll return to install the cables.
Lower Ford Street – Raglan Street – East Street
Please see drawings above of completed works.
Payne Lane and Britannia Street
Please see drawings above of completed works.
Gosford Park – Binley Road – Open Space
We’ve now finished the duct installation in this area. The excavation across Gosford Green took longer than planned due to the heatwave causing the ground to dry and harden, causing delays.
The weekend works across Binley Road was completed in two weekends rather than one.
The works on the Open Space area is now connected to the ducting we installed in November 2025.
We’ll need to return to install the cables, and we’re working with the council to coordinate with their cycle lane works. We’ll communicate a date to residents as soon as possible.
Stonehouse Lane
We’ll be returning to Stonehouse Lane beween 10th and 14th October to complete the final section, tying into the works we started on London Road November 2025. We weren’t able to complete these works on our first visit due to traffic and the cycle lane construction.
We plan to complete on London Road 10th/11th October and Stonehouse Lane over the verge to the footway 12th, 13th and 14th October.
This will complete the duct installation, ready for the cable installation towards the end of October, which will be down in the Hammerhead area of Stonehouse Lane
Terry Road and Roundabouts either end
We plan to start works in this area in the coming weeks and a date will be communicated once confirmed. As this area is where the cycle lane works is being carried out, we’re working with the council on the best approach.