Daily Mail

Oliver Road, Thurrock

  • Excavation and installation of:
    – 3 x 1000m of 33kV single core underground cable within duct
    – 1400m of 125mm medium pressure gas main
  • Installation of on-site water mains consisting of 400m of 180mm hydrant main with in-line hydrants and associated double check valve, 63mm potable water service including meter with leakage monitoring.
  • Design, supply, installation and commissioning of a 33/11kV Primary Substation